Building hazards and controls, ready to check
When the job involves props, scaffold or an old house, Gate Ready adds the hazards (a fall from an edge, collapse during alterations, and asbestos) and controls like these. Each one shows its type.
- IsolateEdge protection (guardrail, mid-rail and toe-board) installed on all open edges before work starts
- AdminTemporary works designed by an engineer; the design is on site
- EngineerProps and bracing installed to the design before cutting or removing members
- AdminProps inspected daily and after any impact or change; not removed until the engineer approves
- IsolateExclusion zone under and around the supported area
- AdminAsbestos register checked, or suspect material sampled and tested, before work starts
- AdminHandover certificate kept on site until the scaffold is taken down (a scaff tag alone is not enough)
A fall of more than 2 m, structural alterations that need temporary support, demolishing a load-bearing element and work that is likely to disturb asbestos are all on the model national list of high risk construction work. Some states add their own items, so check your regulator. Scaffold, an elevating work platform and rescue lines are in the list too. You choose the ones that fit your job. Gate Ready suggests, you review.